Implementation Department#3220 - Integration and Testing

Status:
New
Assignee:
Implementation Department
Estimated time:
15.00 h (Total: 20.00 h)
Tracker:
Deliverable
Priority:
Normal
Due date:
17/05/2017
Start date:
10/05/2017
Spent time:
Created:
29/11/2017 01:26
Milestone:

Skill 1 required?:
no
MoreLess

All the units developed in the implementation phase are integrated into a system after testing of each unit. Post integration the entire system is tested for any faults and failures.

Sub tasks

Task #3245: Create testing scenariosNewImplementation Department

Display previewUpdate

Related tasks:

 
following Pure Waterfall Model - Deliverable #3219: Implementation New Implementation Department 30/04/2017 07/05/2017
precedes Pure Waterfall Model - Deliverable #3221: Deployment of System New Implementation Department 21/05/2017 28/05/2017